Scheduling tasks fed from Python data
=====================================

This example schedules five kitchen tasks.  Each task has a duration and
needs one resource.  Some tasks must follow others.  Python holds the data
and asks Curry for a schedule that fits a horizon of a given length.  It
grows the horizon until a schedule exists and draws that schedule as a
Gantt chart.


1. What the example shows about functional logic programming
-------------------------------------------------------------

Constraint solving by search.  The schedule in

    starts = [ (n, anyOf [0 .. horizon - d]) | (n, d, _) <- tasks ]

gives each task anyOf the start slots that keep it inside the horizon.  The
call anyOf xs is a choice among the elements of xs.  So the one expression
starts means every assignment at once.

Lazy generate and test.  The guard

    all ordered prec && all noOverlap pairs

keeps the assignments where every precedence holds and no two tasks on one
resource overlap.  A failed guard is not an error.  It produces no value.
The Curry side only states the constraints.  It has no loop, no search
state, and no backtracking code.  The runtime does the search.

The order of the guards matters.  The runtime makes a choice only when the
guard needs its value.  The precedence check comes first.  It forces the
starts along the chain of tasks, and a task that starts too soon fails
before any later task gets a start.  The resource check comes second and
sees only the assignments that survived.

Optimization by failure.  A horizon that is too short has no schedule, so
the call yields zero values.  Python counts upward from the longest task.
The first horizon with a schedule is the shortest one.


2. What the example shows about calling Curry from Python
----------------------------------------------------------

The tasks and the precedences are Python data: a list of (name, duration,
resource) tuples and a list of (before, after) pairs.  The driver go.py
passes them to the Curry function schedule with the horizon.  The typed
symbol call converts them: tuples become Curry tuples, lists become
Curry lists, and ints become Curry Ints.

A name is a Python str, always a String, also when it has one character.

One call,

    curry.eval(Sched.schedule(tasks, precedences, horizon))

returns a lazy Results iterator of schedules.  The driver takes the first
one with next().  Taking one answer or breaking out of a loop preserves
the iterator's position.  Use close() or leave a with block to end the
search explicitly.  A horizon with no schedule yields zero values, so
next() returns the default None, and the driver tries the next horizon.
Evaluation turns the schedule into a Python list of (str, int) pairs.
The driver sorts it by start slot and draws the chart.


3. How to run
-------------

Run "make stage" from the root of the repository first.  Then run

    ./run

To try other tasks, edit TASKS and PRECEDENCES at the top of go.py.  If
several schedules of the same length exist, the first one found may differ
from one run to the next.


4. Expected output
------------------

The file expected.out holds the exact output of ./run.  The driver prints
the tasks and the precedences first.  Then it prints one line per horizon:

    horizon 8: none
    horizon 9: mix@0 bake@2 cool@5 frost@7 pack@8

The chain mix, bake, cool, frost, pack has a total duration of 9.  So no
schedule fits 8 slots, and exactly one fits 9.  The chart follows, with one
row per task in order of start:

    slot   012345678
    mix    ##.......  bowl
    bake   ..###....  oven
    cool   .....##..  rack
    frost  .......#.  bowl
    pack   ........#  table


5. Limits
---------

The work depends on how early the guards prune.  The precedences prune
early, so a chain of tasks is cheap.  A chain of eight tasks on four
resources took 0.04 s.
Without precedences only the resource check prunes.  It forces the start of
every task that shares a resource, so the work grows with the slot count to
the power of the task count.  Five tasks on one resource and no precedences
took 0.4 s.  Six such tasks ran out of memory under a 2 GB cap.

A warm run of ./run took 0.2 s.  The first run also compiles the module.
It took about a second.