COMMISSIONING DAILY LOG — VELDEN CONTROLS BV

Project: NWL-VAL-2024-07 — Valencia Distribution Centre, conveyor and sortation system

Engineer: J. de Vries (Velden Controls BV), for Tidewell Fabrication Ltd

Sheet: 3 of 9

Monday 17 March 2025

08:10 — On site. Permanent 400A supply still not energised; temporary generator feeding Bay 1 panel only. Loop checks cannot start on Bay 2.

11:30 — Brisamar electrician (M. Pujol's team) confirms utility connection scheduled for tomorrow.

16:00 — Continued I/O labelling Bay 1 MCP. 142 of 210 points checked.

Tuesday 18 March 2025

09:00 — Utility crew on site. Main switchboard inspection.

14:30 — PERMANENT 400A THREE-PHASE SUPPLY ENERGISED. Measured 401 V L-L, phase rotation correct. Signed off by Brisamar site manager M. Pujol and T. Wójcik (Tidewell).

15:10 — Bay 2 panel powered. Loop checks Bay 1 and Bay 2 to start tomorrow 19 March.

17:00 — Bay 3 zone C4–C7 still suspended pending floor re-levelling. No power applied to Bay 3 drives.

Wednesday 19 March 2025

08:00 — Loop checks Bay 1 started. 58 of 210 points verified by 12:00.

13:15 — Sorter controls software v2.3.1 loaded on redundant S7-1500 pair. Fault F-301 on outfeed lane 22 photo-eye; replaced.

16:40 — Loop checks Bay 2 started.

Supervisor initials: TW — JdV