Dear Priya,

Thank you for your e-mail of 21 February and the Levantina report.

Brisamar does not accept that the Bay 3 slab is outside tolerance. The slab was surveyed by the main contractor on completion in August 2024 and found to be within 5 mm over 3 m. We will send that survey to you when we have it from the main contractor. In the meantime we do not accept CO-3 and we do not accept any extension of time on this ground.

Tidewell's supports are, as you say, adjustable, and Tidewell's tender confirmed that minor deviations could be accommodated. Please proceed with the installation at Tidewell's risk. If Tidewell considers that local grouting is required it should carry this out as part of its installation works.

Please send your cost and time proposal in any event so that we have it on file, but you should not treat this as an instruction.

Regarding the power supply, Marc is chasing the utility and will revert.

Best regards,

Lucía Ortega
Project Director, Brisamar Logistics SA
