Dear Priya,

I refer to your e-mail of 9 March.

Brisamar rejects the extension of time claimed. The utility has confirmed that the switchboard upgrade will be completed and the 400A supply energised by the end of this week. Tidewell is in any event not ready to commission: the sorter is not mechanically complete and, by your own account, work in Bay 3 is incomplete. Any delay to commissioning is the result of Tidewell's late delivery in February and its slow progress in Bay 3, not of the power supply.

Brisamar reminds Tidewell that Mechanical Completion is due on 21 March 2025 and Practical Completion on 25 April 2025. Brisamar will apply liquidated damages under clause 10 from 21 March 2025 if Mechanical Completion is not achieved, and reserves all its rights.

Please do not suspend any work. Any suspension will be treated as a breach of the Agreement.

Regards,

Lucía Ortega
Project Director, Brisamar Logistics SA