Production Batch Plan
M. Okafor · Production
One irradiation slot may serve several orders. The plan works backwards from each delivery time through decay to a single end-of-irradiation target, then checks that target against facility contention.
Batch
- Batch
- BATCH-0912-CT
- Facility
- CT
- Window
- 09-11 08:00–13:30
- Power
- 950 kW
Orders served
- ORD-2291
- Lu-177 · 3.70 GBq
- ORD-2288
- I-131 · 1.11 GBq
- Positions
- 2 of 3 used
Reactor time
- Requested
- 5.5 h
- Calendar
- 5.5 h held
- Conflict
- 1 warning
Backward schedule from delivery
| Order | Delivery | Transit | Cooling | EOI target | Yield model | Margin |
| ORD-2291 | 09-14 06:00 | 4 h | 2.52 d | 4.90 GBq | ROM-CT-Lu177 v4 | +6.1% |
| ORD-2288 | 09-12 08:00 | 3 h | 0.65 d | 1.19 GBq | ROM-CT-I131 v2 | +1.7% |
ORD-2288 margin is inside 2%. A shutdown slip of more than 3 h puts delivery activity under contract. Flagged to the operator on the day-of check.
Commit batchRe-solveSplit order