Building works         ▲ AMBER   ↓ worsening   The asbestos survey added two
Lead: estates                                  weeks; the contractor is
                                               re-sequencing the ground floor to
                                               hold the opening date.
────────────────────────────────────────────────────────────────────────────────
Self-service kiosks    ● GREEN   → no change   All six installed and tested with
Lead: digital                                  the new catalogue.
────────────────────────────────────────────────────────────────────────────────
Staff training         ■ RED     ↓ worsening   No trainer is booked yet.
Lead: people team                              Decision needed: approve the
                                               supplier's quote by Friday.
────────────────────────────────────────────────────────────────────────────────
Stock move             ● GREEN   ↑ improving   The temporary store is ready, a
Lead: collections                              week early.
────────────────────────────────────────────────────────────────────────────────
Reopening event        ▲ AMBER   → no change   Date held; the guest speaker has
Lead: communications                           not yet confirmed.

Ratings as at the end of period 7; the trend is the change since period 6.