Production Batch Plan

M. Okafor · Production

One irradiation slot may serve several orders. The plan works backwards from each delivery time through decay to a single end-of-irradiation target, then checks that target against facility contention.

Batch

Batch
BATCH-0912-CT
Facility
CT
Window
09-11 08:00–13:30
Power
950 kW

Orders served

ORD-2291
Lu-177 · 3.70 GBq
ORD-2288
I-131 · 1.11 GBq
Positions
2 of 3 used

Reactor time

Requested
5.5 h
Calendar
5.5 h held
Conflict
1 warning

Backward schedule from delivery

OrderDeliveryTransitCoolingEOI targetYield modelMargin
ORD-229109-14 06:004 h2.52 d4.90 GBqROM-CT-Lu177 v4+6.1%
ORD-228809-12 08:003 h0.65 d1.19 GBqROM-CT-I131 v2+1.7%
ORD-2288 margin is inside 2%. A shutdown slip of more than 3 h puts delivery activity under contract. Flagged to the operator on the day-of check.
Commit batchRe-solveSplit order

← Dashboard · Production · Batch plan